Rondo I consists of two buildings: a forty-storey glazed tower (building B) located parallel to the Jana Pawła II Avenue and lower, ten-story building A with the facades of opaque frosted glass, located on Swietokrzyska Street. The building was given to use in 2006. As Europe’s first skyscraper Rondo I has been certified LEED Gold in the category of “Existing Buildings” and was the first in Warsaw offers an AAA class areas.
Modernized area:
Ground floor – COSTA COFFEE
Area of modernization: 184,5 sq. m
Date of modernization: 20th of January 2015 – 28th of January 2015
Scope of work:
- Execution of project’s documentation of vases with experts’ arrangements of scripted space for sprinkler’s system,
- Modernization of the sprinkler’s system and the supply of sprinkler heads and piping,
- Execution of complete as-built documentation containing all required protocols and expert’s arrangements.
Floors 2, 3 and 4 – VOLKSWAGEN BANK
Area of modernization: 400 sq. m
Date of modernization: 18th of December 2014 – 27th of January 2014; 20th of May 2014 – 24th of June 2014; 15th of April 2015 – 31st of May 2015
Scope of work:
- Execution of project’s documentation of vases with experts’ arrangements of scripted space for comfort ventilation’s and smoke exhaust’s installations, water and sewage, heating and cooling and sprinkler’s installations,
- Modernization of the comfort ventilation’s and smoke exhaust’s installations, water and sewage system, heating and
- cooling’s and sprinkler’s installations,
- Delivery and installation of system’s new components and equipment such as: fan coil units, air diffusers, exhaust air elements, ventilation equipment, smoke canals, fire dampers, water heaters, sprinkler heads, boxes, piping, technical insulation,
- Measurements and control of comfort ventilation’s and smoke exhaust’s installations and heating and cooling system, pressure tests of heating and cooling and sprinkler’s and hydrant’s installations,
- Execution of complete as- built documentation containing all required protocols and experts’ arrangements.
Floor 7 – EY
Area of modernization: 870 sq. m
Date of modernization: 13th of April 2015 – 18th of June 2015
Scope of work:
- Modernization of the comfort ventilation’s and smoke exhaust’s, water and sewage systems, heating and cooling’s, sprinkler’s and hydrant’s installations,
- Delivery and installation of system’s new components and equipment such as: fan coil units, air diffusers, exhaust air elements, ventilation equipment, smoke canals, fire dampers, water heaters, sprinkler heads, boxes, hydrant boxes, piping, technical insulation,
- Measurements and control of comfort ventilation’s and smoke exhaust’s installations and heating and cooling system, pressure tests of heating and cooling and sprinkler’s and hydrant’s installations,
- Execution of complete as- built documentation containing all required protocols and experts’ arrangements.
Floor 10 – COMPASS
Area of modernization: 1400 sq. m
Date of modernization: 19th of June 2015 – 21th of August 2015
Scope of work:
- Execution of project’s documentation of vases with experts’ arrangements of scripted space for comfort ventilation’s and smoke exhaust’s installations, water and sewage, heating and cooling’s, sprinkler’s and hydrant’s installations,
- Modernization of the comfort ventilation’s and smoke exhaust’s, water and sewage systems, heating and cooling’s, sprinkler’s and hydrant’s installations,
- Delivery and installation of system’s new components and equipment such as: fan coil units, air diffusers, exhaust air elements, ventilation equipment, smoke canals, fire dampers, water heaters, sprinkler heads, boxes, hydrant boxes, piping, technical insulation,
- Implementation of flooding monitoring’s system in the kitchen room by using flooding ‘s sensors and optical – audio signaller,
- Measurements and control of comfort ventilation’s and smoke exhaust’s installations and heating and cooling system, pressure tests of heating and cooling and sprinkler’s and hydrant’s installations,
- Execution of complete as- built documentation containing all required protocols and experts’ arrangements.
Floors 22 i 23 – HSBC
Area of modernization: 2800 sq. m
Date of modernization: 12th of February 2015 – 30th of April 2015
Scope of work:
- Execution of project’s documentation of vases with experts’ arrangements of scripted space for comfort ventilation’s and smoke exhaust’s installations, water and sewage, heating and cooling’s, sprinkler’s and hydrant’s installations,
- Modernization of the comfort ventilation’s and smoke exhaust’s, water and sewage systems, heating and cooling’s, sprinkler’s and hydrant’s installations,
- Delivery and installation of system’s new components and equipment such as: fan coil units, air diffusers, exhaust air elements, ventilation equipment, smoke canals, fire dampers, water heaters, sprinkler heads, boxes, hydrant boxes, piping, technical insulation,
- Implementation of temperature’s monitoring system in the server room by using sensors and GSM gateways – information via SMS to excessive temperature in the room,
- Measurements and control of comfort ventilation’s and smoke exhaust’s installations and heating and cooling system, test of vacuum and pressure precision air conditioning’s system,
- Execution of complete as- built documentation containing all required protocols and experts’ arrangements.
Floor 24 – CBRE
Area of modernization: 1400 sq. m
Date of modernization: 15th of January 2014 – 02nd of March 2014
Scope of work:
- Modernization of the comfort ventilation’s and smoke exhaust’s, water and sewage systems, heating and cooling’s, sprinkler’s and hydrant’s installations,
- Delivery and installation of system’s new components and equipment such as: fan coil units, air diffusers, exhaust air elements, ventilation equipment, smoke canals, fire dampers, water heaters, sprinkler heads, boxes, hydrant boxes, piping, technical insulation,
- Measurements and control of comfort ventilation’s and smoke exhaust’s installations and heating and cooling system, pressure tests of heating and cooling and sprinkler’s and hydrant’s installations,
- Execution of complete as- built documentation containing all required protocols and experts’ arrangements.
Floor 32 – DENTONS
Area of modernization: 1400 sq. m
Date of modernization: 13 of April 2015 – 30th of May 2015
Scope of work:
- Execution of project’s documentation of vases with experts’ arrangements of scripted space for comfort ventilation’s and smoke exhaust’s installations, water and sewage, heating and cooling’s, sprinkler’s and hydrant’s installations,
- Modernization of the comfort ventilation’s and smoke exhaust’s, water and sewage systems, heating and cooling’s, sprinkler’s and hydrant’s installations,
- Delivery and installation of system’s new components and equipment such as: fan coil units, air diffusers, exhaust air elements, ventilation equipment, smoke canals, fire dampers, water heaters, sprinkler heads, boxes, hydrant boxes, piping, technical insulation,
- Measurements and control of comfort ventilation’s and smoke exhaust’s installations and heating and cooling system, pressure tests of heating and cooling and sprinkler’s and hydrant’s installations,
- Execution of complete as- built documentation containing all required protocols and experts’ arrangements.